Friday, June 7, 2013

Empat dikhuatiri terbunuh dalam runtuhan Jambatan Kedua Pulau Pinang - berita bergambar



Dalam kejadian runtuhan sebahagian daripada ‘ramp’ susur keluar Jambatan Kedua Pulau Pinang berhadapan dengan kilang Motorola di sini yang runtuh kira-kira jam 7.15 malam tadi empat orang dikhuatiri terbunuh..

Ini berikutan penemuan sebuah kereta Kelisa yang berwarna putih yang remuk ditimpa runtuhan struktur tersebut..







The Malaysia Insider melaporkan...

Empat orang dipercayai terbunuh apabila sebahagian daripada Jambatan Kedua Pulau Pinang yang masih dalam pembinaan di Batu Maung di sini, runtuh menghempap kenderaan mereka lebih kurang pukul 7.00 malam.

Polis telah menerima panggilan lebih kurang pukul 7.05 malam mengenai runtuhan itu dan bergegas ke tempat kejadian pada pukul 7.15 malam.

Menurut jurucakap polis, sebahagian daripada Penyambung Batu Maung menghubungkan jambatan ke Tun Dr Lim Chong Eu telah runtuh menghempap kenderaan yang melalui berdekatan dengan struktur itu.

Penyiasatan awal menunjukkan keempat-empat orang di dalam kenderaan dipercayai terbunuh serta merta.

Bahagian runtuh merupakan sebahagian daripada jejambat yang menghubungkan lebuh raya ke jambatan di antara dua rusuk konkrit.

Pihak polis telah menutup kawasan tersebut kepada lalu lintas.
Kakitangan Jabatan Bomba dan Penyelamat telah menemui kenderaan yang dihempap dan kini kerja-kerja sedang dijalankan untuk mengeluarkan mangsa daripada kenderaan hancur.

Terdahulu, timbalan pengurus jabatan perhubungan awam dan komunikasi Jambatan Kedua Sdn Bhd (JKSB) Azizi Azizan mengesahkan seksyen Pakej 3A projek Kedua Jambatan Pulau Pinang telah runtuh.

"Itu adalah bahagian yang menghubungkan jambatan kepada lebuhraya Tun Dr Lim Chong Eu," kata beliau kepada The Malaysian Insider dalam satu temu bual telefon.

Seksyen ini masih dalam pembinaan dan kontraktor sepatutnya melengkapkan dan menyerahkan bahagian yang selesai bulan depan, katanya.

"Kerja-kerja pembinaan sedang dijalankan apabila ia berlaku tetapi kita telah mengarahkan dihentikan serta-merta ke atas semua kerja-kerja pembinaan berikutan kejadian itu," katanya.
Ia masih terlalu awal untuk menentukan punca keruntuhan tetapi JKSB akan menjalankan siasatan penuh mengenai kejadian itu.

JKSB juga akan mengeluarkan kenyataan penuh mengenai kejadian itu esok.


The Star pula melaporkan seperti berikut.........

Second Penang Bridge ramp collapses, four in car found dead

GEORGE TOWN: An uncompleted flyover connecting to the still-under-construction second Penang bridge at Batu Maung collapsed at around 7pm Thursday, burying at least one car and a motorcycle under the debris.

Police fear that four people are dead after one car, a white-coloured Perodua Kelisa was found buried under the rubble.

State Fire and Rescue Department confirmed that one motorcyclist, who was earlier trapped under the debris, has been pulled out. He suffered injuries to his head.

State Fire and Rescue Department have mobilised hundreds of firemen from throughout the state as well as volunteers to the scene, including medical personnel.

Firemen are extricating the debris to reach the cars and motorcycles under the rubble, consisting mostly metal scaffolding and steel beams.

Bayan Baru MP Sim Tze Tzin, who was on the scene, said about a 30m-long span of the ramp was believed to have collapsed around 7pm, as work to install concrete boulders to strengthen the structure was ongoing.

He said he was informed a few people may be trapped under the rubble. State executive councillor Lim Hock Seng said the cause of the collapse had yet to be determined.

"We cannot confirm the cause of the accident," he said, adding that a full investigation would be carried out.

Police have began deploying traffic policemen as the incident has caused a severe jam to ensue near the Tun Dr Lim Chong Eu Expressway.

Many motorists have also stopped to look at the debris.

As of 9:30pm Thusrday night, fire department authorities have briefed Sim and Lim.

R. Thilasheni, 24, whose car windscreen was shattered by a falling beam during the incident, was still in a state of shock.

"We were lucky to come out alive. We were only about three seconds away from when the ramp collapsed," she said.

She was travelling with her friend G. Gajashaantini, also 24.

She believed a motorcyclist was trapped under the rubble and said a beam fell onto a car in the incident.

The 24km-long bridge was set for completion next month, the longest bridge in South-East Asia and 20th in the world was supposed to go through road commissioning and testing in August before being officially opened in September.- The Star

Berita asal -ASD

Perbuatan macai yang memburuk-burukkan Lim Guan Eng ekoran daripada kejadian runtuhan di jambatan kedua Pulau Pinang itu melambangkan betapa bodohnya mereka.

Projek tersebut adalah kebanggaan Barisan Nasional yang dirancang semasa pentadbiran Tun Abdullah Ahmad Badawi tetapi diteruskan di zaman Najib iaitu bermula pada 2008.

Pada Ogos 2006, kerajaan persekutuan Malaysia mengatur pelan untuk membina Jambatan Kedua Pulau Pinang yang terkandung dalam Rancangan Malaysia Kesembilan.

Pada 12 November 2006, majlis penanaman cerucuk besi Jambatan Kedua Pulau Pinang yang baru dilakukan oleh Perdana Menteri Malaysia, Dato' Seri Abdullah Ahmad Badawi. Projek ini pernah ditunda selama sembilan bulan kerana masalah reka bentuk dan kenaikan harga barangan binaan.

Projek yang telah 94% siap itu dijangka dibuka kepada umum pada September 2013. Mungkin tertunda lagi berikutan kejadian runtuhan ini... wakaka